SUBSTATION CONSTRUCTION
CEI has completed over a dozen substation projects over the last twenty years. Our past performance history speaks for itself. We are continually used by the City of Redding and other government agencies by offering competitive and accurate bids, a good safety record and quality work. Our workforce has been trained in working in energized substation environments.
CEI has completed over a dozen substation projects over the last twenty years. Our past performance history speaks for itself. We are continually used by the City of Redding and other government agencies by offering competitive and accurate bids, a good safety record and quality work. Our workforce has been trained in working in energized substation environments.
2010/2011 UKIAH, CA ORCHARD SUBSTATION
2006/2007 CITY OF REDDING CANBY SUBSTATION
INSTALLATION OF A FOURTH 115/12KV TRANSFORMER BANK
Cal Electro Inc. provided labor, materials, and equipment for the installation of a 115/12kV transformer, air switches, circuit breakers, oil retention vault, and bus work for the extension of the East Redding Substation. The City of Redding provided all electrical equipment and steel structures.
Contract Amount: 914,450.00
Contract Amount: 914,450.00
2004/2005 City of Redding Moore Substation
Cal Electro Inc. provided labor, materials, and equipment for the installation of a 115/12kV transformer, air switches, circuit breakers, oil retention vault, and bus work for the extension of the East Redding Substation. The City of Redding provided all electrical equipment and steel structures.
Contract Amount: 674,000.00
Contract Amount: 674,000.00
2004 Bechtel Nevada Corporation-Nevada Test Site-Modernization of 138kV substations
Cal Electro constructed a new distribution substation in Mercury, NV. This substation work included excavation of pier foundation up to 7 foot in diameter and 23 feet deep, construction of 25 foot concrete transformer fire walls, installation of 138 kv SF6 breakers and V switches, installation of 15 kv switchgear and control building, and the installation of two 138 kv 32 MVA transformers. Work also consisted of installation of 138 kv SF6 breakers, circuit switches and transformers at Jackass Flats Substation. A big thanks out to Jim kilpatrick at Bechtel Nevada. And a big no thanks to Kieth at "Ham & Taters"
Contract Amount: 3,230,000.00
Contract Amount: 3,230,000.00
2002 City of Redding Switchyard Expansion
CEI expanded the 115 kv switchyard at the City of Redding Power Plant. The work consisted of installation of a 50 MVA transformer, 115 kv SF6 circuit breaker, 115 kv V switches, concrete foundations, duct bank, relay wiring, over one thousand feet of high voltage underground feeders, bus structures and bussing.
Contract Amount: 970,000.00
CEI expanded the 115 kv switchyard at the City of Redding Power Plant. The work consisted of installation of a 50 MVA transformer, 115 kv SF6 circuit breaker, 115 kv V switches, concrete foundations, duct bank, relay wiring, over one thousand feet of high voltage underground feeders, bus structures and bussing.
Contract Amount: 970,000.00
2001 Bechtel Nevada Corporation-Nevada Test Site-Modernization of 138kV substations
CEI provided all technical and professional services including labor, tools, material and equipment for the modernization of four substations located at the Nevada Test Site in Mercury, NV. Scope of work included the replacement of 138kV circuit switches with SF6 gas circuit breakers and the replacement of electromechanical protective relays with solid state microprocessor based protective relays.
Contract Amount: $1,743,000.00
Contract Amount: $1,743,000.00
1999 City of Redding East Substation-Installation of 115/12kV Transformer Bank Number
CEI provided labor, material and equipment for the installation of a 115/12kV transformer, air switches, circuit breakers, and bus work for the extension of the East Redding Substation. The City of Redding provided all electrical equipment and steel structures.
Contract Amount: $409,541.00
Contract Amount: $409,541.00
1998 City of Shasta Lake Knauf Substation
Cal Electro Inc. provided labor and equipment to construct a new 115kV substation, installation of 12.47 kV metering, underground feeders, retention system, and control building. We also installed and commissioned two (2) 115kV transformers and 115kV SF6 breakers.
Contract Amount: 593,000.00
Contract Amount: 593,000.00
1996 City of Redding Texas Springs Substation
CEI built a 115kV substation with switching yard. This substation consisted of installing and commissioning one (1) 115kV/12kV, 32 MVA transformer, 115kV SF6 circuit breakers, 12kV Vacuum breakers, air switches, bus work and control building. The City of Redding supplied all electrical equipment and steel structures.
Contract Amount 1,053,500.00
Contract Amount 1,053,500.00
1995 Airport Transformer Bank Number 1
CEI installed a 115/kV, 32 MVA transformer, air switches, circuit breakers, and bus work for the expansion of the Airport Substation. The City of Redding supplied all electrical equipment and steel structures.
Contract Amount: $442,100.00
Contract Amount: $442,100.00
OTHER CEI SUBSTATION JOBS
2000 Wheelabrator Redding, CA Upgrade Substation
1998 City of Shasta Lake, CA Knauf Substation
1997 City of Shasta Lake, CA Corporate Yard Substation
1991 US Navy China Lake Weapons Center, CA Repair 35 kv Sub.
2000 Wheelabrator Redding, CA Upgrade Substation
1998 City of Shasta Lake, CA Knauf Substation
1997 City of Shasta Lake, CA Corporate Yard Substation
1991 US Navy China Lake Weapons Center, CA Repair 35 kv Sub.






















