Although many of our prime contracts are electrical, CEI specializes in difficult projects requiring knowledge and expertise in mechanical areas. We have the capability to complete many facets of construction, from crane rehabilitation, concrete site improvements, underground utilities , and all electrical phases.
2015 Communications Towers & Vault, Colby Mountain, Forest Ranch, CA
|
|
This project involves constructing a new telecommunication tower and supporting infrastructure at an existing tower site in Tehama County for CHP. Work included transporting, erecting and installing owner furnished pre-manufactured 120 foot tower from W. Sacramento to Colby Mountain. Tower is a self supporting, 4 legged metal improvement. Foundations, separate generator building with emergency backup generator, photovoltaic panel field, propane fuel system, and electrical utilities are also a part.
Contract Amount: $2,089,000.00
Start Date: 4/20/2015
Completion Date: ongoing
Job No.: 1502
Contract Amount: $2,089,000.00
Start Date: 4/20/2015
Completion Date: ongoing
Job No.: 1502
Phase 1 Wastewater Treatment Improvement Project, Biggs, CA
Construction of the Biggs Wastewater Treatment Plan which included the installation of new influent piping and manholes, a spiral mechanical screen, new concrete sewer influent wet well, influent pump distribution system, field piping, valves, flow meter, a new influent sampler, ties into the existing gravity and force main system, electrical services for the new equipment, SCADA system, associated SCADA telemetry, a backup generator, manual bar screen and associated piping modifications, replacement of field valves within the wastewater treatment facility, repair or replace an existing vertical pump, assorted fencing and gates.
Contract Amount: $1,839,000.00
Start Date: 7/1/2014
Completion Date: under construction
Job No.: 1403
Contract Amount: $1,839,000.00
Start Date: 7/1/2014
Completion Date: under construction
Job No.: 1403
2011 Shasta College
CEI installed a gas line at Shasta College. We put our boring machine to the test here, and we were very pleased with the results.
2003 Shasta Crane
CEI rehabilitated a gantry crane for the U.S. Bureau of Reclamation at Shasta Dam
This project consisted of installation of new VSD's, engine generator, automatic rope re-winder, operator controls, wire rope, fuel tank and platform, on the existing 125 ton gantry crane located on Shasta Dam.
Contract Amount $996,000.00
CEI rehabilitated a gantry crane for the U.S. Bureau of Reclamation at Shasta Dam
This project consisted of installation of new VSD's, engine generator, automatic rope re-winder, operator controls, wire rope, fuel tank and platform, on the existing 125 ton gantry crane located on Shasta Dam.
Contract Amount $996,000.00
2003 Folsom Cranes
CEI is modified three cranes for the U.S. Bureau of Reclamation at Folsom Dam
CEI is modified three cranes for the U.S. Bureau of Reclamation at Folsom Dam
2003 Folsom Cranes
This project includes the modification of three cranes, by installing new load cells, VFD's, festoon systems, wire rope, rail foundation, operator controls, and 140 ton trolley. This job is challenging due to the specialized scope of the work, i.e. load testing a 140 ton crane with water weights on Folsom Dam Blvd.
Contract Amount $1,023,500.00
This project includes the modification of three cranes, by installing new load cells, VFD's, festoon systems, wire rope, rail foundation, operator controls, and 140 ton trolley. This job is challenging due to the specialized scope of the work, i.e. load testing a 140 ton crane with water weights on Folsom Dam Blvd.
Contract Amount $1,023,500.00
2002 EID Power House
CEI installed flood protection at the El Dorado Irrigation District Power House.
CEI installed flood protection at the El Dorado Irrigation District Power House.
Work consisted of Removing windows, and installing concrete walls, grout injecting walls, demotion of existing equipment and walls, installing water-tight doors, and erosion control outside the power house. This project was challenging due to the short schedule, and working directly over the American River.
Contract Amount $690,000.00
Contract Amount $690,000.00
2001 Oroville Power House
CEI installed crane controls for the California State Department Of Water Resources
Contract Amount $1,600,000.00
CEI installed crane controls for the California State Department Of Water Resources
Contract Amount $1,600,000.00
1998 Sacramento Tower Bridge
CEI installed crane controls for the California Department Of Transportation
CEI installed crane controls for the California Department Of Transportation
Contract Amount $385,000.00