Powered by Create your own unique website with customizable templates.
Welcome to Cal Electro Inc.
  • CEI HOME
  • Construction Portfolio
    • AIRPORT CONSTRUCTION
    • CALTRANS
    • POWER DISTRIBUTION
    • POWER GENERATION
    • SPECIALTY CONSTRUCTION
    • SUBSTATION CONSTRUCTION
  • Other
    • EMPLOYMENT OPPORTUNITIES
    • TIME CARD

Substation Construction

CEI has over two decades of proven experience in substation construction services, delivering safe, reliable, and cost-effective solutions for complex electrical infrastructure projects. Our highly trained workforce specializes in construction within energized substations, ensuring compliance, safety, and precision at every stage. 

Our commitment to quality workmanship and consistent on-time, on-budget delivery has earned the trust of the City of Redding, WAPA, and other government agencies. Today, CEI is the preferred choice for substation construction and maintenance throughout Northern California. 

Tracy 500kv Substation - COTP Shunt Cap Breaker & Switch Replacement Bay T8, 2025

Project includes removal and replacement of 500KV power circuit breakers, motor operated disconnecting switches, and motor operated ground switches located in Bay T8, as well as the installation of miscellaneous electrical material including conduit, outdoor bus, and control cables. 
​
Contract Amont: $2,237,150.00
ONGOING

Olinda Substation - Station Service Upgrades, 2025

Project includes demo of existing Unit Substation DZA, pad mount transformer, and standby generator, followed by installation of 230kv bay, including motor operated disconnect switch, SSVT's and associated material, as well as a pad mount transformer, ATS, three safety switches, 35kV power cable, a main distribution switchboard and associated steel structures and foundations. 

Contract Amount: $874,185.00
ONGOING

Tracy 500kv Substation - COTP Shunt Cap Reactor & Switch Replacement Bay T10, 2024

Project included removal and replacement of 500kv power circuit breakers, motor operated disconnecting switches, and motor operated ground switches located in Bay T10, as well as installation of a surface trench and associated electrical equipment and site development. 

Contract Amount: $2,319,355.00 

Keswick & Maxwell Substations - Station Service Upgrades, 2021

Project included installation of 230-kV Government-furnished SSVT’s, 115-kV Government-furnished station service transformer and associated material, ATS, safety switches, main distribution panel, and associated station service equipment including yard panels, dry-tape, pad mounted transformers, insulated conductors, conduit, concrete foundations and support structures for station service equipment. CEI provided foundations, galvanized steel structures for electrical equipment, provided and installed precast cable trench and removed cable/equipment after station service cut-over. 

Contract Amont: $2,184,032.00

 
US Army Corp of Engineers MOTCO B606 Inland Substation, 2021

Scope included replacement of the Building 606 transformer and switchgear, overhead transmission lines, and security fencing, as well as other minor site improvements and incidental related work integrations.

Contract Amount: $ 2,274,359.00                                     

Nevada National Security Site DAF & Frenchman Flats Substations, 2021

Project included modernization of two substations located at the Nevada National Security Site in Mercury, Nevada. Scope included building one new identical redundant substation and critical upgrades to a second. CEI provided all technical and professional services including labor, testing, material and equipment for the project.​  ​

Contract Amount:  $4,328,612.38

Folsom UHA Switchgear Replacement WAPA Switchyard, 2017

Project Description:  Remove and replace station service switchgear, UHA, associated protective relay systems, instrumentation transformers and metering. Remove and replace existing concrete foundations and slab for fabricated control building.  Structural metalwork. Remove and replace existing 5 kV cables. Provide contract document management system.  Furnish drawings and data. Provide turn-key interface with existing switchyard and power plant alarm, protection, control and SCADA circuits. Provide communication interface with power plant Central Valley Automated Control System. Provide as-builts, new cable tray directly below existing UHA switchgear, spare parts and training.
Project included removal and replacement of station service switchgear, UHA, associated protective relay systems, instrumentation transformers and metering, 5kv cables, structural metalwork, and existing concrete foundations and slab for fabricated control building. CEI provided turn-key interface with existing switchyard and power plant alarm, protection, control and SCADA circuits, as well as communications interface with power plant Central Valley Automated Control System. 

Contract Amount: $3,546,209.22


Mustang Substation Bank 1 Replacement, California Polytechnic State University, 2016

Project included replacing the existing Mustang Substation 70kV-12.47kV, 10MVA transformer with a 15MVA transformer and associated transmission equipment, on the California Polytechnic State University campus in San Luis Obispo, California.

Contract Amount: $458,000

Shasta Switchyard, Flanagan and Keswick Substations Upgrades, 2013

Project included removing and disposing of existing switches, conductors, wave traps and insulators assemblies, installation of government-furnished 230-kV disconnect switches, motor group-operated and 230-kV disconnect switches, selector/tandem type, motor group-operated, ACCR Drake conductor, high temperature fittings, and insulators assemblies. CEI provided associated jumpers, hardware, and conduit. We would like to say thanks to Bob Toenjes Ross Mcfate, Gary Johnson, and Don Kiel, It was a pleasure working with you guys.

Contract Amount:   $1,500,000.00


​Orchard Substation, Ukiah, 2011

Project included construction of a new 115kv substation. Scope included foundations, 40 MVA 115/12kv transformers, 115kv SF6 breakers, 115kv switches, 115kv transformer, 27,000' of 12kv 1100KCM cable, and installation of one 30'x90' pre-manufactured control building. All major electrical equipment was owner supplied. 

Contract Amount: $2,980.000.00


CEI Substation Portfolio

2025      Tracy 500kv Substation - COTP Shunt Cap Breaker & Switch Replacement Bay T8, WAPA

2025      Olinda Substation - Station Service Upgrades, WAPA

2024      Tracy 500kv Substation - COTP Shunt Cap Breaker & Switch Replacement Bay T10, WAPA 

2021      Keswick and Maxwell Substation - Station Service Upgrades, WAPA
​
2021      Building 606 Electrical Substation Upgrade, MOTCO 

2021      Nevada National Security Site DAF & Frenchman Flat Substation

2020      DWR; Unit Substation, San Luis Obispo Operations and Maintenance 

2019      4160V to 12kV Conversion, CSU San Jose 

2017      Folsom UHA Switchgear Replacement WAPA Switchyard 

2017      Electrical Substation Reliability Improvements, CSU San Jose

2016      Mustang Substation Bank 1 Replacement, Cal Poly

2013      Shasta Switchyard, Flanagan, and Keswick Substations Upgrades

2014      Substation Infrastructure Project, City of Gridley

2013      Arden Del Paso Substation 

2013      BART Substation Transformer Replacement 

2013      Orchard Substation, Ukiah

2013      Canby Substation 

2013      COR Moore Substation

2013      SAC 2E/2F Substation

2012      COR Substation

2012      East Redding Substation

2012      Bart Substation South San Francisco

2011      Orchard Substation, Ukiah

2004      Bechtel Nevada Corporation, Nevada Test Site - Modernization of 128kv Substations

​2002      City of Redding Switchyard Expansion

2001      Bechtel Nevada Corporation, Nevada Test Site - Modernization of 128kv Substations

2000      Wheelabrator Redding, CA Upgrade Substation


1999      City of Redding East Substation Installation of 115/12kv Transformer bank Number

1998      City of Shasta Lake, CA Knauf Substation 


1997      City of Shasta Lake, CA Corporate Yard Substation 


1996      City of Redding Texas Springs Substation

1995      Airport Transformer Bank Number 1

1991     US Navy China Lake Weapons Cetner, CA Repair 35kv Substation
Proudly powered by Weebly
  • CEI HOME
  • Construction Portfolio
    • AIRPORT CONSTRUCTION
    • CALTRANS
    • POWER DISTRIBUTION
    • POWER GENERATION
    • SPECIALTY CONSTRUCTION
    • SUBSTATION CONSTRUCTION
  • Other
    • EMPLOYMENT OPPORTUNITIES
    • TIME CARD